When a full kitchen renovation called for new electrics from the ground up, the homeowner needed an electrician who could work in step with the builders — running first-fix cables before the walls were plastered, returning once the kitchen was fitted, and dealing with whatever the existing wiring threw up. Arthur Blackwell delivered exactly that: a systematic two-phase rewire that brought the property up to standard and wired every appliance to its own dedicated circuit.
The kitchen renovation required a complete electrical strip-out and rebuild. Eight appliances — induction hob, top and bottom ovens, extractor hood, washing machine, dishwasher, fridge, and wine fridge — each needed a dedicated circuit. The scope also included recessed LED downlights throughout the kitchen ceiling, under-cupboard lighting, and two new wall lights on the extension facade.
Working in sequence with the building contractor, Nexgen completed first-fix cabling in March 2026 before the walls were plastered — labelling every appliance position so builders preserved the correct knockout positions. Six non-compliant joints were identified and re-made to BS 7671 before the walls were closed. Second-fix and consumer unit installation followed in May.
Individual fused spur isolation for every kitchen appliance — each circuit run back to a labelled breaker in the new consumer unit.
Full consumer unit replacement providing protected circuits for the complete property, with all existing ring mains retained and tested.
Seven recessed downlights through the ceiling void, a dedicated under-cupboard lighting circuit, and two exterior wall lights on the extension.
Six non-compliant joints found during first-fix and re-made to BS 7671 before plastering — defects that would otherwise have been buried inside the finished walls.
Every project demands a tailored approach. Our scope encompasses the full spectrum of electrical infrastructure — from initial assessment through final commissioning — ensuring seamless integration and long-term reliability.
Eight dedicated fused spurs for induction hob, top and bottom ovens, extractor hood, washing machine, dishwasher, fridge, and wine fridge — each individually protected and labelled.
FuseBox consumer unit installed and commissioned, replacing the existing unit — dedicated circuits for all kitchen appliances, property ring mains retained and tested.
Seven recessed downlights wired through the kitchen ceiling void on a dedicated lighting circuit — positioned and roughed-in during first fix before the ceiling was boarded.
Dedicated circuit for under-cupboard LED lighting — independently switched from the ceiling downlights for flexible kitchen task lighting.
Two new wall lights wired to the extension facade — cabling roughed-in during first fix and terminated on the second fix visit.
Six non-compliant cable joints identified during first-fix inspection and re-made to BS 7671 standard before plastering — defects that would have been concealed inside the finished walls.
Complex electrical projects rarely follow a straight line. Our engineers thrive in high-constraint environments — designing solutions that protect operations, meet deadlines, and stand the test of time.
The project involved coordinating electrical work across two distinct phases — first fix before plastering, second fix after the kitchen was fitted — while working around the building contractor's programme. During the first-fix inspection, six non-compliant cable joints were discovered in the existing installation. Rectifying these before the walls were closed added scope mid-project and required a judgement call on how to handle cabling that did not meet current BS 7671 standards.
Arthur Blackwell completed the first-fix cabling in a single visit, labelling every appliance knockout position on the walls so the building contractor could work around them without disturbing the cable routes. The non-compliant joints were re-made on the same visit — keeping the programme intact. Second-fix followed once the kitchen was installed: consumer unit replacement, all appliance spur connections, lighting circuits energised, and all circuits tested and signed off.
Every phase is planned, sequenced, and executed with precision. From initial assessment through to commissioning, we keep every milestone visible and every deadline on track.
1 day
1 day
All appliance circuit cables run, lighting positions roughed-in. Six non-compliant joints identified and re-made to BS 7671 before plastering. Every knockout position labelled for the building contractor.
1 day
1 day
Consumer unit replaced. All eight appliance fused spurs terminated and tested. Downlights, under-cupboard lighting, and external wall lights commissioned. All circuits tested and signed off.
From groundworks to final commissioning, these images document the precision and care that goes into every Nexgen installation.
More Residential Projects
Browse our completed commercial electrical installations across the South East — each one delivered to the same standard of documentation, compliance, and programme management.

Full domestic electrical installation for a local Taplow homeowner — consumer unit replacement, new circuits throughout, lighting, power, and final accessories. Tested, certified to BS 7671, and handed over spotless.

Full luxury domestic rewire at a prestigious property within the grounds of Calcot Park Golf Club, Berkshire. Nexgen delivered a comprehensive electrical upgrade combining premium LED lighting design, smart home integration, external feature and security lighting, CCTV, and a fully compliant new consumer unit.
Stay updated with our work across London and the Home Counties. See behind-the-scenes content, project updates, and industry insights.
Whether you're planning an infrastructure upgrade, retrofit, or new installation, our team would love to discuss how we can help.