KARIUM EV charging bay — Rolec charger live at Capitol Building, Bracknell
Completed
Featured
Commercial
Project // Active
Commercial Property Sector

Capitol Building EVBracknell

400V three-phase EV charging infrastructure for the KARIUM car park at Capitol Building, Bracknell. Seven Rolec pedestals, fourteen charging sockets, Proteus GRP distribution kiosk, 49m 150mm² SWA sub-main, and Monta OCPP 1.6J smart charging platform. EIC certified 15 May 2026.

14 Charge Points Live

Seven Rolec pedestals providing fourteen EV charging sockets — installed, commissioned, and certified at the KARIUM car park, Capitol Building, Bracknell.

49m SWA Sub-Main

150mm² armoured cable routed through car park trench, planted-border conduit, and internal raised floor void — a single continuous run with no intermediate joints.

250A Dedicated DB

Bespoke Proteus GRP distribution kiosk with 250A TPN board, DP isolator, and SPD — connected to the Capitol Building LV supply.

Monta Smart Charging

OCPP 1.6J smart charging platform — RFID and app control, dynamic load balancing, and remote monitoring configured and live from day one.

NICEIC Approved|Part P Certified|24/7 Emergency|4 Active Projects
Projects/
Categories/
Commercial EV/
/
Capitol Building EV Charging — Bracknell
Commercial EV Infrastructure

CommercialScale.EngineeredRight.ManagedSmart.

From sub-main design to smart charging management — a complete 400V EV infrastructure solution for one of Bracknell's premier commercial addresses.

Seven pedestals. Fourteen charging sockets. A 250A dedicated distribution board and 49m of 150mm² SWA sub-main — infrastructure built to serve this car park for the next decade. BS 7671:2018+A3:2024 compliant, with independent cable calculations by Nicholas Owen Associates Ltd and an EIC certificate issued on completion.

Monta OCPP 1.6J smart charging platform with RFID and app control, dynamic load balancing, and remote monitoring. Ongoing management from day one — and a 180-page O&M manual handed to the client so the estates team can manage the installation for its entire operational life.

01

Commercial Scale

Seven pedestals, fourteen charging sockets — a 250A dedicated distribution board and 49m of 150mm² SWA sub-main built to serve this car park for the next decade.

02

Engineered to Standard

BS 7671:2018+A3:2024 compliant installation. Independent cable calculations by Nicholas Owen Associates Ltd. EIC certificate issued on completion.

03

Managed Platform

Monta OCPP 1.6J smart charging platform. RFID and app control. Dynamic load balancing. Remote monitoring and ongoing management — day one and beyond.

04

Documented Handover

180-page O&M manual delivered at handover. EIC certificate EIC-20260514-QPSS issued 15 May 2026. Three-year Rolec warranty registered — everything the estates team needs to manage the installation for its operational life.

A Managed Estate Requiring Managed Charging

Capitol Building is managed by one of the country's leading commercial property practices. When the brief arrived to design and install a full EV charging infrastructure across the KARIUM car park, the requirement was straightforward: fourteen charge points, professionally installed and properly documented, with a smart charging platform configured from day one so the estates team would never be left managing an installation they didn't understand.

Before a single cable was ordered, Nexgen completed a full LV switchgear compliance check at the Capitol Building Main Switch Panel, commissioned independent cable calculations from Nicholas Owen Associates Ltd, and finalised RAMS documentation prior to mobilisation. Factory QA testing of the GRP feeder pillar and distribution equipment was completed before delivery to site. It is the kind of pre-construction discipline that turns a six-week programme into a six-week delivery.

Project Profile
Proteus GRP distribution kiosk on base at Capitol Building KARIUM car park, Bracknell

Capitol Building, Bracknell · March–May 2026

From Basement Switchgear to Car Park Bay — Every Metre Engineered.

Delivering fourteen EV charging sockets to the KARIUM car park at Capitol Building required resolving a cable route from the building's basement Main Switch Panel to the rear car park — 49 metres of 150mm² SWA through three distinct environments, a bespoke Proteus GRP enclosure, and a Monta smart charging platform configured for this site. The result is a future-ready commercial EV infrastructure Nexgen would put its name to.

01

Site Survey & Design

LV switchgear compliance verified at existing Main Switch Panel. 150mm² SWA cable sizing independently calculated by Nicholas Owen Associates Ltd. Route survey across all three environments — car park, planted border, raised floor void.

02

49m Sub-Main Installation

150mm² SWA armoured cable pulled as a single continuous run: basement MSP to car park trench, through planted-border conduit, and internal raised floor void — no intermediate joints.

03

Proteus GRP Kiosk

Bespoke 250A TPN Proteus distribution kiosk crane-delivered and installed. DP isolator, SPD, and twelve-way distribution board wired. All seven EV charger circuits individually protected with MCB and RCBO.

04

Monta Smart Charging

Seven Rolec pedestals commissioned and enrolled on the Monta OCPP 1.6J platform. RFID and app control configured. Dynamic load balancing active. 3-year Rolec warranty registered and 180-page O&M manual delivered.

“Nexgen delivered a complete, well-documented EV installation from survey through to platform handover. The O&M manual was a level above what we expected from an electrical contractor.”

— Site Manager · Commercial Property Management

Scope of Work

Precision Engineering, Comprehensive Delivery.

Every project demands a tailored approach. Our scope encompasses the full spectrum of electrical infrastructure — from initial assessment through final commissioning — ensuring seamless integration and long-term reliability.

Civil Groundworks

Block paving lifted and set aside, cable trench excavated across the KARIUM car park, hazard covers installed throughout, and block paving fully reinstated with KARIUM EV green guide lines on completion.

Proteus GRP Distribution Kiosk

Bespoke 250A TPN Proteus kiosk crane-delivered — base prepared, kiosk positioned, DP isolator, SPD, and twelve-way distribution board installed and connected to the Capitol Building LV supply.

49m 150mm² SWA Sub-Main

49-metre 150mm² armoured cable in a single continuous run: car park trench from kiosk, conduit through planted border, and Capitol Building's internal raised floor void to charger distribution positions — no intermediate joints.

MCB & RCBO Protection

Individual MCB and RCBO protection installed for each of the seven charger circuits within the Proteus kiosk — ensuring individual fault protection for every charging bay.

Rolec Pedestal Installation

Seven Rolec pedestals installed at designated KARIUM bay positions, individually connected, tested, and commissioned. Fourteen charge points certified and live.

Monta OCPP 1.6J Platform

All seven chargers enrolled on the Monta OCPP 1.6J smart charging platform. RFID and app control configured, dynamic load balancing activated, remote monitoring live from day one.

EIC Testing & Commissioning

Full BS 7671:2018+A3:2024 testing of all seven EV charger circuits — insulation resistance, earth fault loop impedance, RCD operation, and protective conductor continuity verified with calibrated Megger test equipment. EIC certificate EIC-20260514-QPSS issued 15 May 2026.

Periodic Inspection & Testing

Commercial EV charging installations require periodic inspection and testing to maintain BS 7671 compliance and warranty validity. Nexgen offers scheduled periodic testing for all charger circuits — keeping the installation compliant, the Rolec warranty intact, and the property manager's duty of care covered.

Six Weeks on a Live Commercial Estate

The KARIUM car park remained partially open throughout the programme. Traffic management and safe working zones were established before groundworks began — cable trenches were protected with hazard covers, and charger bay positions were staked out and agreed with the building management team before any block paving was lifted. The estate continued to function around the programme.

The most technically demanding element was the sub-main cable run. Rather than introduce joints — which add potential failure points to an underground installation — Nexgen pulled 49 metres of 150mm² SWA armoured cable as a single continuous run: from the basement Main Switch Panel, through the planted border conduit, across the Capitol Building internal raised floor void, and into the Proteus GRP kiosk. O-PEN protection devices were installed at each charger position. Foundation bases, draw pits, and final circuit runs were completed to programme, with fire sealing at all penetrations before sign-off.

Engineering Excellence

Meeting Every Challenge Head On.

Complex electrical projects rarely follow a straight line. Our engineers thrive in high-constraint environments — designing solutions that protect operations, meet deadlines, and stand the test of time.

Challenges & Solutions

01

49m Sub-Main Route Through Three Distinct Environments

Challenge

Routing 150mm² SWA armoured cable from the Capitol Building basement Main Switch Panel to the rear car park required crossing three distinct environments — an open car park surface needing civil groundworks and full block-paving reinstatement, a narrow planted border requiring conduit through established planting, and the building's internal raised floor void. Each environment imposed different handling and fixings requirements for the heavy-gauge armoured cable.

Solution

Nexgen sequenced the installation to tackle each environment in turn. Civil groundworks and cable draw-in were completed as a single 49m continuous pull with no intermediate joints. Hazard covers protected open trenches throughout; the KARIUM car park remained partially operational at every stage. Block paving was fully reinstated on completion with green KARIUM guide lines at every EV bay.

02

Independent Engineering Sign-Off Before Procurement

Challenge

A commercial EV sub-main of this scale required independent confirmation of cable sizing before any materials were ordered. Commissioning a third-party cable calculation report added time to the pre-construction phase that had to be managed within a fixed programme.

Solution

Independent cable calculations were commissioned from Nicholas Owen Associates Ltd before procurement. The report confirmed 150mm² SWA for the 49m run. Factory QA testing of the Proteus GRP kiosk and distribution equipment was completed before delivery to site — so commissioning ran to programme without last-minute substitutions or delays.

03

Smart Charging Platform Onboarding on a Managed Estate

Challenge

Enrolling seven chargers on the Monta OCPP 1.6J platform — with RFID access controls, dynamic load balancing, and remote monitoring — needed to be co-ordinated as part of the commissioning sequence on a live managed estate, without extending the programme.

Solution

Monta onboarding was completed in the same session as EIC testing. All seven chargers were enrolled, RFID access configured, and dynamic load balancing activated before the estate was handed back. The property management team received a 180-page O&M manual covering every circuit, every setting, and every maintenance requirement.

Project Timeline

A Methodical Approach to Delivery.

Every phase is planned, sequenced, and executed with precision. From initial assessment through to commissioning, we keep every milestone visible and every deadline on track.

  • Phase 1

    March 2026 · ~3 days

    Phase 1

    March 2026 · ~3 days

    SiteSurvey&ComplianceCheck

    completed

    Existing LV switchgear at the Capitol Building Main Switch Panel assessed for spare capacity and compliance with current regulations. Charger positions confirmed with the property management team. Independent cable calculations commissioned from Nicholas Owen Associates Ltd for the 49m 150mm² SWA sub-main route.

  • Phase 2

    March–April 2026 · ~1 week

    Phase 2

    March–April 2026 · ~1 week

    Sub-MainDesign&CableProcurement

    completed

    Cable calculation report received and verified — 150mm² SWA confirmed for the 49m run from basement MSP to rear car park GRP position. Proteus kiosk specification finalised: bespoke 250A TPN twelve-way board in GRP walk-in enclosure. Materials procured and delivery of Proteus kiosk coordinated with site programme.

  • Phase 3

    April 2026 · ~1.5 weeks

    Phase 3

    April 2026 · ~1.5 weeks

    CivilGroundworks&CableRoute

    completed

    Block paving lifted across the KARIUM car park, cable trench excavated from kiosk position, 150mm² SWA armoured cable drawn in. Conduit installed through the planted border. Internal raised floor void accessed — SWA routed on cable tray through plant room to basement MSP. Block paving reinstated to original condition with KARIUM EV green guide lines marked.

  • Phase 4

    April 2026 · 2 days

    Phase 4

    April 2026 · 2 days

    ProteusGRPKioskInstallation

    completed

    Proteus distribution kiosk crane-delivered and positioned on prepared base. DP isolator, SPD, and 250A TPN twelve-way distribution board installed and wired. SWA cable terminated and connected to Capitol Building LV supply. Kiosk distribution board dressed, labelled, and circuit directory completed.

  • Phase 5

    April–May 2026 · ~1 week

    Phase 5

    April–May 2026 · ~1 week

    ChargerInstallation&FinalCircuits

    completed

    Seven Rolec pedestals installed at KARIUM bay positions. Individual final circuits — MCB and RCBO protection — run from Proteus kiosk to each charger position. Fire sealing completed at all penetrations. Circuit labelling confirmed against directory. Cable management dressed.

  • Phase 6

    May 2026 · 2 days

    Phase 6

    May 2026 · 2 days

    EICTesting,Commissioning&Handover

    completed

    Full installation tested to BS 7671:2018+A3:2024 using calibrated Megger test equipment — insulation resistance, earth fault loop impedance, RCD operation, and protective conductor continuity verified at every charger circuit. All seven Rolec chargers enrolled on Monta OCPP 1.6J — RFID access configured, dynamic load balancing activated, remote monitoring live. EIC certificate EIC-20260514-QPSS issued 15 May 2026. Three-year Rolec warranty registered. 180-page O&M manual delivered to property management.

Project Gallery

Captured at Every Stage.

From groundworks to final commissioning, these images document the precision and care that goes into every Nexgen installation.

4 more images

Fourteen Charge Points. Certified. Managed. Documented.

EIC certificate EIC-20260514-QPSS was issued 15 May 2026 following full BS 7671:2018+A3:2024 testing of every charger circuit — insulation resistance, earth fault loop impedance, RCD operation, and protective conductor continuity verified at each bay. All fourteen sockets functional-tested. Three-year Rolec warranty registered to the estate.

The Monta OCPP 1.6J platform went live from day one: RFID and app access configured, dynamic load balancing protecting the Capitol Building LV supply, and remote monitoring giving the property management team full visibility of every session. The 180-page O&M manual delivered on handover gives the estates team everything needed to manage the installation across its operational life — and Nexgen's ongoing periodic inspection and testing service keeps it BS 7671 compliant and Rolec warranty-valid for the years ahead.

Client Testimonial

Straight From the Client.

The measure of our work is the confidence our clients carry forward. Here's what they had to say.

“Nexgen delivered a complete, well-documented EV installation from survey through to platform handover. The O&M manual was a level above what we expected from an electrical contractor.”
S

Site Manager

Commercial Property Management

Commercial Property Estate

Project Tags

EV ChargingCommercial EVCommercial400V Three-PhaseRolecCivil WorksMonta OCPPNICEIC Certified

Get Started

Ready to discuss your project requirements?

🎯

EV Charging

Free EV Site Survey

Book a no-obligation EV charging infrastructure survey for your commercial premises.

ctaBook Survey →
📢

EV Grant Guide

UK EV Chargepoint Grant Support

Find out if your business qualifies for up to £500 per socket under the Workplace Charging Scheme.

campaignDownload Free Guide →

Project Details

Status
completed
Scope
Design & Install
Timeline
6 weeks
Location
Bracknell, Berkshire
Capacity
7 × Rolec / 14 sockets
Sector
Commercial Property
Connect With Us

Follow Our Latest Projects

Stay updated with our work across London and the Home Counties. See behind-the-scenes content, project updates, and industry insights.

LinkedInFacebookTwitterInstagram

Interested in a Similar Project?

Whether you're planning an infrastructure upgrade, retrofit, or new installation, our team would love to discuss how we can help.

03333 356 037

Mon-Fri 8am-6pm

projects@nexgen-electrical.co.uk

We reply within 24 hours

Get a QuoteMore Projects
NEXGEN Electrical Innovations

Expert electrical engineering and installations for commercial and industrial frontiers. High-voltage solutions delivered with precision.

From residential EICR compliance and EV charging installations to industrial power systems and 24/7 emergency response — certified UK engineers, built for every scale.

Company

  • About Us
  • Our Team
  • Careers
  • News & Updates
  • Case Studies

Services

  • Residential
  • Commercial
  • Industrial
  • Emergency
  • EV Charging

Support

  • Contact
  • Get a Quote
  • Maintenance Plans
  • FAQs
  • Support Centre

24/7 Emergency

Online

Emergency Response

Always Available

Call Emergency Line
2026 NEXGEN ELECTRICAL INNOVATIONS. ALL RIGHTS RESERVED.
PRIVACY POLICYTERMS OF SERVICELICENSING
POWERED BY ADU-DEV SOLUTIONS