Biffa Workshop Farnham — 3-phase electrical installation
Completed
Featured
Commercial
Project // Active
Waste Management & Sustainability Sector

Biffa Workshop3-Phase Electrical

Design and installation of a new fully operational 3-phase electrical supply system for Biffa's workshop facility in Farnham, Surrey — the start of our work with Biffa.

3-Phase Install

DNO Connection

NICEIC Certified

Workshop Ready

NICEIC ApprovedPart P Certified24/7 Emergency13 Projects Showcased
Client Project

Biffa.NoTimeToWaste.

Biffa turned to our team with a clear task: design and install a new, fully operational 3-phase electrical supply system for their brand new workshop in Farnham, Surrey. Delivered in 8 weeks, on budget, to specification.

Biffa plc is one of the UK's leading waste management companies, committed to sustainability, recycling, and enabling the circular economy. When they needed a trusted electrical contractor for their Farnham facility, they came to our team, and this Farnham project was where our work with Biffa began.

The scope covered the full electrical fit-out of a new workshop: 3-phase distribution, high-level lighting, emergency lighting and exit signage, small power circuits, and 3-phase supplies for roller shutter doors, machinery, and welding equipment. Every installation was designed, executed, and certified to the highest standards.

01

Where It Began

The Farnham workshop was the first project we delivered for Biffa.

02

3-Phase Design

Full 3-phase electrical supply system designed and installed from first principles — including distribution, protective devices, and capacity sized for Biffa's workshop operations.

03

Workshop-Ready Delivery

Lighting, emergency systems, small power, and 3-phase machinery circuits — every system required for a fully operational workshop, installed and commissioned within 8 weeks.

04

On Budget. On Time.

£65K. 8 weeks. Zero programme overruns. We delivered to the brief Biffa set.

Biffa Chose Our Team. We Delivered.

The Farnham workshop was the start of our work with Biffa. Biffa needed a team they could trust with a new facility: one that would design the system correctly, install to a high standard, and hand over on time. We delivered all three.

Scope of Work

Precision Engineering, Comprehensive Delivery.

Every project demands a tailored approach. Our scope encompasses the full spectrum of electrical infrastructure — from initial assessment through final commissioning — ensuring seamless integration and long-term reliability.

3-Phase Distribution System

Full 3-phase electrical supply system — new distribution board, protective devices, and mains cabling designed and installed to BS 7671 specification.

High-Level LED Lighting

High-level LED lighting installation throughout the workshop — specified for industrial lux levels, energy efficient, and designed around Biffa's operational layout.

Emergency Lighting & Exit Signage

Full emergency lighting system and exit signage installed throughout — maintained fittings at all escape routes and risk areas, commissioned to BS 5266.

Small Power Circuits

Small power circuit installation for tools, chargers, and workshop equipment — wired, dressed on containment, and fixed into final positions per design.

3-Phase Machinery & Equipment Circuits

Dedicated 3-phase circuits for roller shutter doors, machinery, and welding equipment — sized and protected to meet Biffa's workshop operational requirements.

Testing, Commissioning & Certification

Full circuit testing, commissioning, and BS 7671 certification across all installed systems — formally handed over to Biffa at practical completion.

Designed Right. Installed Right. No Rework.

The design stage was thorough by necessity — every cable sized from load data, every protective device selected from specification sheets, every item location confirmed with the client before a single cable was pulled. The RAMS document was reviewed and signed before mobilisation. When the team arrived on site, they knew exactly what to build and how to build it.

Engineering Excellence

Meeting Every Challenge Head On.

Complex electrical projects rarely follow a straight line. Our engineers thrive in high-constraint environments — designing solutions that protect operations, meet deadlines, and stand the test of time.

The Challenge

Designing and installing a complete 3-phase electrical system for a brand new workshop required precise load calculations, accurate cable sizing, and careful sequencing of installation work to meet an 8-week programme. With Biffa's operations relying on the new facility being ready on schedule, there was no margin for programme overruns or rework.

Our Solution

Our team carried out a detailed design stage from the outset — calculating current carrying capacities, specifying cables and protective devices from load data, and planning item locations within the workshop. A thorough walkthrough with the client and a completed RAMS document ensured all site-specific requirements were captured before construction began. High-quality materials and meticulous workmanship ensured the installation progressed cleanly to handover.

Project Timeline

A Methodical Approach to Delivery.

Every phase is planned, sequenced, and executed with precision. From initial assessment through to commissioning, we keep every milestone visible and every deadline on track.

  • Phase 1

    2 weeks

    Design&RAMS

    completed

    Initial client meeting, load calculation, electrical system design, item location planning, risk assessment, and RAMS approval — all completed before mobilisation.

  • Phase 2

    2 weeks

    FirstFix&Containment

    completed

    Cable containment installation, first-fix wiring for all circuits, and distribution system rough-in — routed and dressed per design drawings.

  • Phase 3

    3 weeks

    SecondFix&SystemsInstallation

    completed

    High-level lighting, emergency lighting, small power, and 3-phase machinery circuits installed and fixed into final positions.

  • Phase 4

    1 week

    Testing,Commissioning&Handover

    completed

    Full circuit testing, BS 7671 certification, commissioning of all systems, and formal handover to Biffa at practical completion.

Captured at Every Stage.

From groundworks to final commissioning, these images document the precision and care that goes into every Nexgen installation.

3 more images

On Time. On Budget. Ready From Day One.

The Biffa Farnham workshop was handed over inside 8 weeks and within the £65K budget. Every circuit certified, every system commissioned. Biffa's operations team had a fully functional facility from day one.

Project Tags

3-PhaseCommercial WorkshopClient ProjectNew Build Services

More Commercial Projects

Projects Like This One

Browse our completed commercial electrical installations across the South East — each one delivered to the same standard of documentation, compliance, and programme management.

DHL Reading distribution hub — completed operational facility
CommercialCompleted
01 NOV 2025

DHL Reading Distribution Hub

Full Cat B electrical fit-out for DHL's Reading parcel sorting and distribution hub, encompassing conveyor power infrastructure, Schneider LV distribution, office fit-out, and emergency systems across a high-throughput logistics facility.

Reading, Berkshire·Commercial
View Project →
Medivet Watford veterinary practice — completed electrical fit-out
CommercialCompleted
01 AUG 2025

Medivet Watford Veterinary Practice

Full electrical fit-out for Medivet's flagship 18,000 sqft Watford veterinary practice — a dual-wing healthcare facility requiring dedicated fuseboards for each wing, healthcare-grade compliance, and precise coordination with Woodhouse Workspace across a live construction programme.

Watford, Hertfordshire·Commercial
View Project →
Ladbrokes Woking retail electrical fit-out — completed trading floor
CommercialCompleted
01 APR 2026

Ladbrokes Woking — Retail Electrical Fit-Out

Full electrical Cat B fit-out for Ladbrokes' 12,000 sq ft FTSE100-standard Woking retail betting shop across two concurrent wings — delivered live in an operational retail environment.

Woking, Surrey·Commercial
View Project →
Herschel Grammar School — electrical maintenance contract
CommercialCompleted
04 MAY 2026

Herschel Grammar School — Electrical Maintenance Contract

Ongoing electrical maintenance partnership with Herschel Grammar School — a co-educational grammar school with academy status in Slough. From the first meeting to today, trust and reliability are the defining pillars of this relationship.

Slough, Berkshire·Commercial
View Project →
Connect With Us

Follow Our Latest Projects

Stay updated with our work across London and the Home Counties. See behind-the-scenes content, project updates, and industry insights.

Interested in a Similar Project?

Whether you're planning an infrastructure upgrade, retrofit, or new installation, our team would love to discuss how we can help.