Medical Grade
Medical-grade electrical installation compliant with HTM 06-01 for specialist veterinary equipment.

Full electrical fit-out for Medivet's flagship 18,000 sqft Watford veterinary practice — a dual-wing healthcare facility requiring dedicated fuseboards for each wing, healthcare-grade compliance, and precise coordination with Woodhouse Workspace across a live construction programme.
Medical Grade
Theatre Supply
Clinical Lighting
NICEIC Approved
When Woodhouse Workspace were awarded the Medivet Watford flagship fit-out, they brought Nexgen Electrical Innovations on board as electrical contractor — a partnership built on a shared commitment to programme certainty and quality delivery. The result is a 18,000 sqft dual-wing veterinary practice with electrical infrastructure engineered to the exacting standards healthcare environments demand.
Medivet Watford is one of the most significant veterinary healthcare facilities of its kind in the region — a purpose-designed practice spanning a north wing and south wing, each operating as a functionally independent zone with its own dedicated fuseboard. The dual-fuseboard design was a deliberate engineering decision: it provides electrical resilience, simplifies fault isolation, and supports the different operational loads of consulting, surgical, and imaging areas without cross-dependency.
Nexgen's installation team worked closely with Woodhouse Workspace from pre-construction planning through to commissioning, navigating the particular challenges of a healthcare environment — including strict sterile zone protocols, sensitive equipment in active areas, and the coordination demands of a large, multi-trade fit-out delivered on a fixed programme.
Dedicated fuseboards for the north and south wings ensure electrical independence between zones — supporting different operational loads and simplifying fault isolation without cross-dependency.
Full BS 7671 compliance with healthcare-specific provisions — including medical IT systems, equipotential bonding, and protection against electromagnetic interference in imaging areas.
End-to-end electrical fit-out across an 18,000 sqft dual-wing facility — from main intake through to final fix, testing, and commissioning certificates at practical completion.
Pre-construction sequencing and parallel-wing installation strategy ensured electrical first-fix never constrained the follow-on trades — delivering to Woodhouse's programme milestone by milestone.
Woodhouse Workspace are a main contractor whose reputation depends on the subcontractors they bring with them. When they were awarded the Medivet Watford flagship fit-out — a prestigious, high-specification healthcare environment — they needed an electrical contractor they could trust to perform at the same level. Nexgen Electrical Innovations had already demonstrated that standard across previous programmes delivered together, and it was that track record that secured the appointment.
The brief was demanding: an 18,000 sqft dual-wing veterinary practice with healthcare compliance requirements, a fixed programme, and an end-client — Medivet — whose standards for their flagship facility left no room for compromise. Nexgen's appointment was a decision by Woodhouse, not Medivet. That distinction matters: it reflects the trust that had been built between the two contractors through consistent, accountable delivery.
Every project demands a tailored approach. Our scope encompasses the full spectrum of electrical infrastructure — from initial assessment through final commissioning — ensuring seamless integration and long-term reliability.
400A TPN main distribution board with metering and protection, serving both wings from a consolidated intake — with independent sub-distribution for north and south zones.
Separate fuseboards for the north and south wings providing independent electrical circuits, fault isolation, and load management tailored to each zone's operational requirements.
Medical IT panel installation, equipotential bonding in treatment and surgical areas, and RCD protection throughout — compliant with BS 7671 and healthcare premises guidance.
LED lighting specification across consulting rooms, surgical suites, imaging areas, reception, and staff welfare — designed to CIBSE guidance with appropriate colour rendering and lux levels.
Full cable tray, conduit, and containment installation across both wings — coordinated with structural, mechanical, and fit-out trades to maintain programme sequence.
Complete second fix including accessories, socket outlets, data provisions, and final connections to clinical equipment power supplies throughout the practice.
BS 5266-compliant emergency lighting installation across all areas, including maintained fittings at escape routes, exits, and clinical risk zones.
Full NICEIC-compliant testing regime with EICRs, commissioning certificates, and operation and maintenance documentation provided at practical completion.
Veterinary healthcare facilities present a category of construction challenge that sits apart from standard commercial fit-outs. Sterile zones, sensitive imaging equipment, and the presence of animals in adjacent areas during later stages of fit-out all impose constraints on when, where, and how trades can work. Noisy or vibration-intensive activities — cutting containment, drilling, pulling cable through tight conduit runs — required careful scheduling to avoid clinical areas that were being handed over progressively to the Medivet team.
Nexgen's site supervisors worked in close coordination with Woodhouse's project manager to maintain a live access schedule, adjusting sequence as different areas became available and others became restricted. It required a level of situational awareness and flexibility that not every electrical contractor can sustain across a 16-week programme — but it is exactly the kind of environment in which Nexgen's site management approach performs at its best.
Complex electrical projects rarely follow a straight line. Our engineers thrive in high-constraint environments — designing solutions that protect operations, meet deadlines, and stand the test of time.
Delivering a full electrical fit-out inside a live veterinary healthcare construction programme introduced constraints that a standard commercial fit-out does not carry. Sterile zones and sensitive clinical equipment in adjacent areas required careful sequencing of noisy or disruptive works. The dual-wing layout meant two parallel installation programmes running simultaneously, with first-fix in the north wing proceeding alongside structural works still completing in the south — demanding precise coordination with Woodhouse's site management team and a clear understanding of which areas were accessible at any given point in the programme.
Nexgen's pre-construction team produced a detailed installation programme sequenced wing-by-wing and zone-by-zone, with clear access windows agreed with Woodhouse before mobilisation. Running parallel installation teams in north and south wings allowed both programmes to advance simultaneously without cross-trade conflicts. Where clinical sensitivity required it, we scheduled noisy containment works outside core hours and used temporary screening to protect adjacent areas. Equipment procurement was managed to just-in-time delivery, keeping plant rooms clear and the programme moving.
Every phase is planned, sequenced, and executed with precision. From initial assessment through to commissioning, we keep every milestone visible and every deadline on track.
2 weeks
2 weeks
Detailed M&E survey, design review, healthcare compliance assessment, equipment procurement, and installation programme issued to Woodhouse Workspace.
6 weeks
6 weeks
Parallel first-fix installation across north and south wings — cable tray, conduit, containment, and distribution cabling to all zones including clinical, welfare, and reception areas.
5 weeks
5 weeks
Main LV board installation, dedicated north and south wing fuseboard fit-off, sub-distribution cabling, and clinical equipment circuit connections.
3 weeks
3 weeks
Second fix accessories, lighting and small power final fix, emergency lighting installation, full circuit testing, EICRs, O&M documentation, and witnessed commissioning.
From groundworks to final commissioning, these images document the precision and care that goes into every Nexgen installation.
Medivet Watford opened on programme. The electrical installation — from the main LV intake through to the final emergency lighting fitting in the surgical suite — was complete, tested, and certified at practical completion. Woodhouse received a full O&M operation and maintenance pack completed, including data sheets of materials used, as-built drawings, all certification and commissioning details, ready for handover to Medivet's estates team.
For Nexgen, this project represents the standard we hold ourselves to in healthcare environments: technically correct, programme-certain, and delivered in a way that makes our client — Woodhouse — look exactly as good as they need to. It is a project we are proud of, and a partnership we intend to continue.
More Commercial Projects
Browse our completed commercial electrical installations across the South East — each one delivered to the same standard of documentation, compliance, and programme management.

Full Cat B electrical fit-out for DHL's Reading parcel sorting and distribution hub, encompassing conveyor power infrastructure, Schneider LV distribution, office fit-out, and emergency systems across a high-throughput logistics facility.

Full electrical Cat B fit-out for Ladbrokes' 12,000 sq ft FTSE100-standard Woking retail betting shop across two concurrent wings — delivered live in an operational retail environment.

Design and installation of a new fully operational 3-phase electrical supply system for Biffa's workshop facility in Farnham, Surrey — a landmark project that established Nexgen as Biffa's preferred electrical partner.

Exclusive electrical maintenance contract for Herschel Grammar School — a co-educational grammar school with academy status in Slough. From first meeting to ongoing partnership, trust and reliability are the defining pillars of this relationship.
Stay updated with our work across London and the Home Counties. See behind-the-scenes content, project updates, and industry insights.
Whether you're planning an infrastructure upgrade, retrofit, or new installation, our team would love to discuss how we can help.